A MAJOR plank in the argument for the Western Isles proposed electricity
grid link is the effect on employment in the islands.

Your editorial cites a claimed figure of 3500 new jobs (“Doubt over isles
green power cable must end”, The Herald, March 31). This figure, which is
found in the joint Scottish Government/Department of Energy & Climate
Change (DECC) report, wildly exaggerates the likely effect on permanent
employment of the new link.

The report calculates a figure of just over 3500 full-time equivalent jobs
(FTEs) in 2030. However, while FTEs may at first sight appear to measure
jobs created they are in fact a statistical construct that treats temporary
(for example, construction) and permanent (for example, maintenance) jobs
separately, and then adds the temporary and permanent FTEs together to get
an overall figure. Of the 3500 FTEs nearly 70% are due to temporary jobs
created while the wind, wave and tidal farms are being constructed. Fewer
than 1100 of the FTEs were attributed to ongoing activities.

More than 80% of these ongoing FTEs arise from projected wave and tidal
developments – 1000MW of wave capacity and 300MW of tidal. These
projections for wave and tidal energy are highly speculative and the
projects may well not materialise at all. The consultants stated that “wave
and tidal technology is still at an early stage of development … it is
acknowledged that technical and commercial feasibility at commercial scale
is still a number of years away”. Even if these developments do eventually
go ahead they will require additional grid capacity and are not relevant in
considering the current proposal.

Wind farms account for the rest of the projected FTEs, amounting to fewer
than 200 ongoing FTEs from 500MW of capacity in 2030. However, in
calculating ongoing FTEs the consultants assume that a full-time job for 10
years equates to 1 FTE and, crucially, that wind farms will be operational
for 25 years. So each permanent job has been credited with 2.5 FTEs, and
200 permanent FTEs equate to only 80 full-time jobs at any time.

The upshot is that the Scottish Government’s own consultants’ report
projected fewer than 80 full-time jobs arising from the ongoing operation
of wind farms in the Western Isles in 2030. That – not the 3500 FTEs – is
the most that can be relied upon when considering the case for the new cable.

Andrew Bain,
1 Stafford Street, Helensburgh.


SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

1 Comment

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *