A windfarm developer’s decision to take contentious plans to the Scottish
Government has been described as an “affront to local democracy”.

As previously reported in the Advertiser, Wind Prospect lodged an appeal
after Midlothian Council failed to reach a decision on the proposed
development of nine turbines at Mount Lothian Moss, near Penicuik, within
four months of submission.

Infuriated local councillors last week pledged to do everything in their
power to persuade Scottish Ministers to refuse the application.

Council leader Owen Thompson (SNP) told the planning committee: “It’s
deeply disappointing that the applicant has chosen to take the action that
they have. They have essentially taken the decision out of the hands of the
committee, denying the local residents, who would have represented views to
a pre-application hearing, the chance to have their say.”

Commenting on the Mount Lothian wind farm appeal, Wind Prospect Development
Manager Karen Thorburn said: “Wind Prospect Developments, on behalf of EDF
Energy Renewables, submitted an appeal to the Scottish Government for
non-determination of its planning application for the Mount Lothian wind
farm, submitted to Midlothian Council in January this year.

“The planning committee was expected to consider the application by the end
of May, within the 16 week determination period from the date the planning
application was submitted. The decision to lodge an appeal was taken as the
council did not determine the application within the statutory 16 week
period and did not request for that period to be extended.

“Additional survey work was carried out in the vicinity of the Mount
Lothian site to prepare for the appeal and there was a further opportunity
for the local community to express their views about the project as part of
the process.

“We are committed to the Mount Lothian proposal and the substantial
benefits it could deliver to Midlothian. The 20.7 megawatt (MW) project
would produce enough low carbon electricity to supply the needs of around
11,000 homes.* Additionally, over its 25 year lifetime, this project could
generate around £2.5 million for local community and environmental
initiatives, as well as deliver further benefits for the wider local
economy. During our consultation it became clear that many people in the
local community recognise the substantial benefits this project could bring
and we hope these can be fully realised.”

Read full story in this week’s Advertiser. Out now.


SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *