Planning bosses are recommending the latest wind farm application for
Peeblesshire is turned down.

Stevenson Hill Wind Energy Limited want to erect eight turbines above
Romanno Bridge.

Since a pre-application notice was first served by the company two years
ago, the development has been scaled back from an original 25 turbines.

But the reduced application for eight of the 100-metre-high structures has
still met with fervent opposition.

A total of 125 letters of objection have been tabled with Scottish Borders
Council. And statutory consultees such as Historic Scotland, the Scottish
Rights of Way Society and neighbouring Midlothian Council, have also raised
their concerns.

Community councils in Peebles, Eddleston and Manor, Stobo and Lyne, as well
as Lamancha, Newlands and Kirkurd have also posted strong objections.

Scottish Borders Council’s own archaeology officer has also opposed the bid
over the site’s proximity to four scheduled monuments – Wether Law Cairn,
Romanno Mains Barrows, Drum Maw Settlement and Whiteside Hill Fort.

Concerns have also been raised about the visibility of the turbines, which
would run along Green Knowe, Hag Law and Wether Law hills, from as far away
as Glentress.

Planning officer John Hiscox is recommending members of the local
authority’s planning committee refuse the application when it comes before
them.

He said: “Hag Law does not conform to the usual requirements for wind farms
in terms of its landscape and visual impacts.

“The Cloich Hills are small and the turbines would dominate them in terms
of scale; containment is poor due to the nature of the landscape meaning
that the turbines would be highly visible from many vantage points; the
linear nature of the scheme and the placement of turbines on the ridges of
distinctive hills is at odds with the subtle and attractive nature of the
locality; the proposed access, infrastructure and the turbines would relate
poorly to the landscape, would compete with the settings of several
monuments and would cause adverse visual impacts in relation to the
Scottish National Trail.”

A separate application for 18 turbines on an adjacent site at Cloich Forest
is currently going through the appeal process.

A public inquiry will take place towards the end of May at Peebles Hydro
before a decision is made.

Mr Hiscox said: “Cumulative impacts with the Cloich scheme are highly
relevant, particularly because the two schemes are a visual mismatch – the
designs of each are very different.

“Furthermore, there is strong public opinion expressed within the
objections that identifies with these concerns.

And he added: “It is primarily the relationship between the development and
the settlements at Romanno Bridge and Halmyre, but to a certain extent the
relationship with Mountain Cross and West Linton that causes a high level
of concern relating to visual impact.”

“Each of these settlements would have a new and strong visual relationship
with the development which would appear to march along the ridgeline and
create a sense of dominance – the wind farm would not maintain the current
relationship between the settlements and the hills but would make a new and
powerful visual statement.”


SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *