Perth-based utility giant SSE will begin work next week on installing a new
electricity cable between Lerwick and Bressay which will run through a duct
bored below the seabed in a first for Scottish inter-island cables in the UK.
Specialist contractor Stockton Drilling will bore and line a 20 centimetre
duct that will run horizontally across a distance of just over 500 metres,
beneath the mouth of Lerwick harbour at a depth of 15 metres below the seabed.
Most existing power cables serving island communities around the UK are
laid directly on the seabed where their position is highlighted via markers
on the shore, charts and navigation systems.
The new method, which could be used in the future on other suitable short
cable crossings, reduces risk of damage to the cable, brings safety
benefits and enables faster, lower cost replacement of the cable when
required.
The use of this technology for the replacement of one of the two existing
11 kilovolt cables which connects Bressay with the hub of Shetland’s
electricity network at Gremista follows the development by SSE’s Hydro
Electric Power Distribution division of a new framework to assess the costs
and benefits of different approaches to installing, protecting and
maintaining its submarine cables.
Adam Bain, SHEPD Investment Manager, said: “Submarine distribution cables
play a critical role for our customers, particularly by providing a
lifeline service to 59 island communities around the north and west of
Scotland.
“Last year, we carried out a review of the way we manage these links to
make sure we are able to identify the right approach in every case. To
achieve the best solution for our customers, we need to take account of the
specific conditions at every location, the risk of conflict with other
users of the seabed and the need to ensure that the costs passed on to
energy consumers are justified.
“For Bressay, this review identified the opportunity to take advantage of
improving technology by extending the application of a method that has been
used before for road, railway and river crossings. The result should be an
improved power supply for customers in Bressay and a saving for bill-payers
across the north of Scotland over the lifetime of the cable duct.”
It is not expected that customer power supplies will be affected during the
works.