By Cheryl Peebles

St Andrews University’s windfarm plans have been dealt a blow by
councillors’ refusal to let a cable be laid linking it to the national grid.

The university asked for the go-ahead to run a 33,000 volt cable nine miles
underground between St Andrews and Kenly, near Boarhills, where it wants to
build six turbines.

Energy produced by the 328ft turbines would be used to power its buildings,
including laboratories where world-class research is conducted and student
residences.

However, Fife Council’s north east planning committee refused its planning
application due to concerns about traffic disruption, impact on residential
amenity and insufficient information about how trees would be protected
along the route via Stravithie, Lathockar and the A915.

It also again refused to amend a condition attached to the planning consent
already issued for the turbines, which would have allowed work to start on
site before agreement is reached with the Ministry of Defence on radar
mitigation.

Many were worried about the impact of the cable, including fears about the
perceived health risk from electromagnetic fields, and councillors
criticised the university’s lack of communication with the public.

The university said the committee had disregarded robust assessments of its
own planning, transport, structural and environment officials, the Scottish
Government, the Scottish Environment Protection Agency and Scottish Natural
Heritage.

A spokesman said: “What this decision confirms, however, is that the
university was right not to engage in any detailed consultation with the
community before plans were approved.

“Until planning experts and councillors are able to agree on what’s
possible, we would simply be consulting on thin air.

“Without that clarity what is now at stake is our best chance to counter
the damaging effects of future energy price rises and protect local jobs.

“We will consider our position once we have had opportunity to review the
full judgement.”

The university has already warned that the project has been put at risk by
a delay in agreeing a mitigation scheme with the MoD to prevent
interference with radar at Leuchars.

However, planning consent allowing work to start on site may be issued
imminently by a Scottish Government reporter as the university has
challenged an earlier refusal by the committee to amend the radar condition.

During its deliberations, several members of the committee criticised the
university’s lack of engagement with the public over the cable planning
application.

Committee member Councillor Elizabeth Riches said: “I think it’s absolutely
disgraceful that the university chose to ignore not one, not two but three
community councils who are statutory consultees.

“Not one of them has had the courtesy from the university to explain what
it is they are trying to do, to give some reassurance.

“As a result people have had to object because they do not know what is
going on.”

Council planner Martin Patrick said the university was not required to
conduct pre-application consultation and the committee was reminded that
similar infrastructure works could be conducted by public bodies without
the need for planning permission.

Mr Patrick also insisted people’s concerns had been taken very seriously
before a recommendation was made that the application be approved.

The committee did, however, approve an amendment to one condition in
relation to the windfarm which had the affect of renewing planning
application, due to expire in October, for three years.


SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *