Lewis Wind Power (LWP) – a joint venture between engineering and
construction group Amec Foster Wheeler and EDF Energy Renewables – has
bought new wind farm acreage on the Isle of Lewis as it seeks to sell
output into the wider UK grid via a planned sub-sea cable.

LWP’s acquisition of Uisenis Wind Farm for an undisclosed amount gives it
the ability to install 45 turbines with a generating capacity of 162 megawatts.

This would be enough to power 124,000 homes and would be the biggest
renewable energy development in the Western Isles.

Combined with its nearby Stornoway Wind Farm project which has planning
permission for 36 turbines totalling 180 MW, LWP says the combined 342 MW
of capacity brings it just shy of that needed to underpin construction of a
power cable to the Scottish mainland.

Matthieu Hue, Chief Executive, EDF Renewables – part of the nuclear-power
colossus EDF Group – said: “This strengthens the case for an interconnector
to the mainland which will unlock the economic potential of the Western
Isles and secure the development of the island’s renewables sector.”

LWP said it hopes the two projects will be able to enter the next UK
government auction round for supplying low-carbon electricity.

Garry Morton, Commercial Director, Amec Foster Wheeler said: “The ownership
of the two wind farms, Stornoway Wind Farm and Uisenis Wind Farm, will
bring benefits to the island through community benefit, employment and
local procurement.

“There will also be an option offered to the local council to take a stake
in the project, which is a similar opportunity to that offered to the
Stornoway Trust on the Stornoway Wind Farm.

Cllr Angus Campbell, Leader of Western Isles Cooncil, said: “The
acquisition of Uisenis Wind Farm by Lewis Wind Power presents a fantastic
opportunity to see this wind farm constructed and deliver significant
benefits both to the local community and the Western Isles as a whole with
an option for the council to purchase a significant stake in the project.

“This is welcome news that can only strengthen the case for the
construction of the interconnector. “


SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.