By Ann O’Loughlin

A farmer has got orders halting works to connect a windfarm in Co Sligo to an electricity substation in Co Leitrim after a High Court judge ruled it was incorrectly decided the works do not require planning permission.

http://www.breakingnews.ie/ireland/sligo-windfarm-works-halted-following-high-court-ruling-789450.html

 

 


SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.