The target to generate 100 per cent of electricity used in Scotland from
renewable sources by the end of this year will be missed, but should be
achieved soon after with several big schemes in development, writes Dr
Richard Dixon
By Richard Dixon
The UK has just experienced over a month when no coal was burned to make
electricity, the first time since coal-fired power stations were built.
When Longannet power station’s turbines stopped spinning in 2016 that was
the end of 115 years of coal burning for power in Scotland.
Around the world, coal-fired power production is in terminal decline and in
some places it is already cheaper to build new renewable power generation
than to keep running a gas-fired power station.
Last year three-quarters of new generation capacity build around the world
was renewables, principally solar and wind. Even under pro-coal Donald
Trump, renewables will overtake coal for US electricity production this year.
The only major fossil-fuel power station left in Scotland, the gas-fired
station at Peterhead, is running at much-reduced capacity and likely to
close in the next few years.
We have two nuclear stations, but the two reactors at Hunterston have
hardly run in the last two years because of cracking in their cores and are
currently shut down, quite possibly never to start again.
We are in the midst of an energy revolution. It moves quite slowly so you
may not have understood that the power that flows when you flick a switch
today is very different from the power that flowed 30 years ago. And that’s
great because taking the carbon out of our electricity is essential in the
fight against climate change.
Also essential is substituting electricity from renewables for fossil fuels
in heating and transport. Energy industry staff are essential workers in
this lockdown period, keeping power flowing. Construction work on new
renewable energy schemes has stopped for now, but it will surge back.
I remember helping persuade the energy minister in 2004 to set Scotland’s
first renewable electricity target at 17.5 per cent by 2010, five per cent
more than currently in production, a target her civil servants told her was
“very brave”. I had argued for a target of 25 per cent and indeed that was
the figure when we did get to 2010. By 2011 it was a third.
Today, renewable energy produces 90 per cent of the electricity we use in
Scotland and more of it includes ownership by communities. Because of
planning delays and lack of support from the UK Government, we won’t quite
reach the target of 100 per cent by the end of this year but big schemes
already under construction and in the pipeline mean it won’t be long before
we do.
Of course some renewable energy is different from traditional
fossil-fuelled energy. While tidal energy is as predictable as, well, the
tides, wind and wave power are less so.
So when we reach the 100 per cent target we will have the capacity to make
all the electricity we need but some days we will be making a thumping
great excess and exporting it to England and Northern Ireland, and some
days we will be importing power through those same connections. There are
plans for a connection to Norway, to create an even more balanced system by
linking to their huge hydro-power resources.
We shouldn’t stop when we reach the 100 per cent target, we should power
straight through, and invest in both more renewables and more energy
storage in a big way, so that on every day we are making all of our
electricity from wind, wave, solar, tidal and hydro-power, and on most days
we are making money by selling the surplus to the rest of the UK and beyond.
.Dr Richard Dixon is director of Friends of the Earth Scotland
Read more:

SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *