The Scottish Government reporter has overturned Highland Council’s refusal of a wind farm planning application, despite widespread local opposition.
The north planning committee also learned today that operators Energiekontor have already said they want to increase the height of the wind turbine tips.
Chairwoman Maxine Morley-Smith branded the developers “sneaky” and “greedy”, warning that locals will be very unhappy with the Scottish Government decision.
‘A difference of opinion’
Strathrory wind farm in Ardross, Alness, was rejected by councillors last June.
Proposals for the seven-turbine wind farm attracted more than 50 objections from the local community.
The main issue under debate was the visual impact of the development on the area, which already has five wind farms.
In a motion tabled by Ms Morley-Smith, the council argued that the development would have a significant detrimental visual impact, contrary to Policy 67 of the Highland-wide Local Development Plan. The motion won by nine votes to three.
However, the Scottish Government has upheld an appeal from Energiekontor, and granted planning permission.
Are local voices heard?
Now, council planners say Energiekontor has already made plans to vary its application.
Last week, the operator served notice that it will apply for a modification to allow larger blade tip heights.
They say this change is due to lower than expected wind speeds on site.
“The developers are already coming back and asking for more,” said Ms Morley-Smith.
“It’s pure greed. It’s very sad to see a development going down this route, which people will find sneaky. I don’t like it.”