In the week when Britain saw the “highest-ever” level of potential wind generation, there was a record of wasted energy, costing millions.
A new report by LCP Delta suggests in the week commencing 3rd October, the grid saw the highest ever available wind generation, peaking at 17.6GW of potential wind energy generated in the evening of the 5th October.
However, constraints on the transmission network meant only 14.1GW of this was able to be used with the rest being turned down.
The authors of the report note that the energy system experienced the second-highest ever wind curtailment in a single week, peaking at 4.5GW of turn-down actions on the 6th October.
It is estimated that this combined wasted energy could have powered more than five million households for a week.
Analysts say that as a result of the curtailment on wind and the need to fire up gas, coal and biomass power plants, the energy system had to pay £27 million across the week, a cost that is ultimately put onto customer energy bills. https://www.energylivenews.com/…/highest-ever-wind…/

SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *