Offshore windfarm operators have asked for a five year extension to start work on its East Lothian site due to ‘industry uncertainty’ – a month before permission runs out.
Seagreen Wind Energy (SWEL) were given the go ahead to bring power from 36 planned wind turbines onto shore at the former Cockenzie Power Station site as part of its Seagreen 1A project in 2020.
At the time part of the conditions required work to begin within five years of permission being granted. But with delays to creating the final wind turbines the firm is now asking for a new start date estimated between 2029 and 2032.
In a report provided to the local authority SWEL said consents granted to the project phase needed to change because of delays.
It said: “Due to uncertainties in the Offshore Wind Farm (OWF) industry and challenges specifically facing the development of the final 36 turbines and associated infrastructure consented as part of Seagreen Alpha and Bravo, but not yet constructed, SWEL are proposing an extension of the
construction window for Seagreen 1A.”
Seagreen Wind Energy Ltd is a joint venture between SSE Renewables and Total Energies which was awarded exclusive development rights in the Firth of Forth by The Crown Estate in 2010. https://www.midlothianview.com/news/cockenzie-windfarm-operator-seeks-five-year-delay?fbclid=IwY2xjawL6AohleHRuA2FlbQIxMQABHoE1MZ8Sr4BYIScS5gn9X4kUulCK8UG6FlH_mbaeYbOB8UgVbKxhGWVUZK03_aem_xqV1raNeSSSrDPLfo5rNRw

SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *