By Graeme Strachan

A radar mitigation row looks likely to spell the end of a six-turbine
windfarm on the outskirts of Forfar.

The Govals windfarm, which is just off the A90 trunk road, was previously
refused in May 2013 before the decision was successfully appealed.

The Scottish Government Reporter approved the application in December 2013,
subject to 22 planning conditions, which included a ban on work starting
until a “radar mitigation system” had been agreed with the Ministry of
Defence (MoD).

Such a system is a scheme designed to mitigate the impact of the
development upon the operation of the Watchman Primary Surveillance Radar
at RAF Leuchars and the air traffic control operations of the MoD.

The timescale for work to start on the windfarm – meeting all conditions –
is December, otherwise the controversial planning application will lapse.

The applicant, David Cooper – on the advice of agent Green Cat Renewables,
recently proposed an amendment that argued work should be able to start but
that no turbines would be built until the radar mitigation scheme was approved.

They argued that if they started work and no radar approval was forthcoming
in the next four years they would restore all of the land where there was
building work, which would have included the laying of new roads, cables
and turbine foundations in preparation for the windfarm.

Ray Gibson, spokesman for Angus Communities Windfarm Action Group, said:
“The applicants and his agent showed utter contempt to the planning system
wanting to start work immediately.

“That was despite the fact that they have been speaking to the MoD for
seven years regarding radar without any success.

“And no evidence was provided that a solution was in sight.

“They also said that they would restore the area – roads, cabling, turbine
foundations – if no MoD agreement could be reached by 2020.

“But they took no account of concerns of residents who faced the
possibility of a double dose of heavy construction traffic, noise and dirt.”

Angus Council planning chief Iain Mitchell said: “Through its commencement
this development could potentially lead to cumulative capacity being
unavailable for other renewable developments to fulfil this contribution
within Angus.

“For these reasons the proposed amendment could undermine Angus Council’s
ability to contribute towards Scottish Government renewable energy targets
and objectives to deliver a low carbon economy.”

It now appears unlikely that a deal will be thrashed out with the MoD
before the planning application lapses in December.


SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

2 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *