by David McPhee
Payments made to onshore wind farms hit a record high last month.
Figures provided by the Renewable Energy Foundation (REF) show that
constraints payments paid to Scottish onshore wind farms hit £30.9 million
in March.
The figure was described as a “growing problem” by the REF, the UK charity
that first drew attention to constraint payments in the wind energy sector.
The Scottish Government confirmed it “was aware” of recent issues affecting
the Scotland to Great Britain (GB) interconnector.
John Constable, director of REF, said: “Constraint payments to wind power
are a continuing and it seems still growing problem.
“Furthermore, the prices demanded and received by wind power continue to
exceed the lost income by a large margin, meaning that wind farms make more
money per unit of electricity when prevented from generating than when
selling to a customer.
“That can’t be right. It is obvious that the regulator should not permit
excess reward on this scale.”
Constraints payments are amounts paid to energy providers when an excess of
energy is being supplied to the grid.
Often, due to the inefficiency of Scotland’s grid system and the remoteness
of many wind farms, the energy they generate cannot then be transported
elsewhere.
In many instances, onshore wind operators will be asked by the National
Grid to power down to prevent them producing an excess of energy that
cannot be used.
Each time this happens the wind farm in question will receive a sizable
constraint payment through the Renewables Obligation.
The £30m price tag for powering down is the largest to date, beating the
£28m payout in September last year.
Payments have rocketed over the last five years, when they averaged two or
three million pounds a month.
Scottish energy minister, Paul Wheelhouse, claimed that new electricity
infrastructure connecting Scotland and the UK would “reduce the need for
constraint payments to operators when the grid is unable to transmit power”.
He added: “We are aware of recent faults in the operation of this key new
interconnector.
“The GB electricity system operator, National Grid, is clearly aware of
this, and efforts continue to restore the link to full service which should
help alleviate some of the current constraints and the need for payments.
“The importance of continued grid investment to facilitate transmission
cannot be overstated and this need, and other associated issues associated
with our energy transition, are featured in our Networks Vision Statement,
which we published just over a month ago.”