By Martin Williams Senior News Reporter
HOUSEHOLDS are facing a huge hike in their energy bills after a record
surge in subsidy payments to switch off Scottish wind farm turbines partly
caused by them producing too much power, an analysis has found.
In the two months of this year, £69 million was paid out in constraint
payments, according to research by the Renewable Energy Foundation which
described it as an “extreme spike”.
This is four times greater than the previous most expensive
January-February period on record, which was in 2016.
The money is given out as compensation to energy firms for turning off
turbines when the network is unable to cope with the power they produce.
The payments which kicked in in 2010, come when wind power in Scotland
exceeds local demand but cannot be exported to England due to insufficient
grid infrastructure.
REF said the surge in payments was partly because of strong winds, which
means farms are generating too much power.
It is also said it was because wider network reinforcement is “unable to
keep pace with wind sector growth in Scotland where government continues to
approve wind farms in spite of the constraints”.
Last year, the total paid was £130 million, which was at that point the
largest to date and the REF say that 2020 is likely to be a record year.
The payments are made by the National Grid but charged to consumers and
added to electricity bills.
A high-voltage submarine power cable between Scotland and England was
supposed to help to cut the figure by allowing energy to be exported south
of the border and keeping the turbines on more regularly.
But Italian telecom systems firm Prysmian, which manufactured cables for
the £1 billion Western Link project, said on January 10 that it had failed.
It came back into operation on February 7 but it was the third failure in
three years.
But REF said that after the link was repaired, constraint costs remained as
high during the latter part of February as they were during the outage
partly because of high winds.
National Grid paid Scottish wind farms to switch off while the cable has
been out of action, leaving customers to foot a bill.
Dr John Constable, director of REF, said: “In spite of expenditure on grid
reinforcement and new lines such as the Western Link, the electricity
system is failing to keep up with the development of wind in Scotland,
resulting in very high costs to consumers. Government both at Holyrood and
Westminster must share the blame. Meanwhile, heads or tails, the energy
companies win handsomely.”
The GMB trade union, has said that the payments are creating a “subsidy
sandwich for a renewables industry” that is treating bill payers with
contempt.
After the latest outage on the Western Link which connects Scottish wind
farms via Hunterston to England and Wales the energy regulatory Ofgem
launched an investigation into National Grid and ScottishPower, the
Glasgow-based arm of Spain’s Iberdrola, over the subsea power cable’s
delivery and operation.
The joint project, which was billed at the time as the world’s largest
subsea interconnecting power cable, was originally due to be completed in
late 2015 but electricity did not start flowing through until December 2017.
It started at less than full capacity in 2017 after problems during
construction. The line has suffered six faults since then, taking it out of
action for months at a time.
Ofgem said in January that it would “review the performance” of National
Grid and ScottishPower and whether they breached their operating licences
through the late completion of the scheme. The regulator said it would also
“examine potential breaches relating to the operation of the cable”.
It has the power to fine them up to 10 per cent of their turnover.
The Western Link runs from Ayrshire to north Wales via a 239-mile subsea
route to the Wirral peninsula and a 20-mile stretch underground. It is
designed to carry 2.2 gigawatts of electricity, enough to power four
million homes.
Prysmian handed the project to National Grid and Scottish Power late last
year and has booked €165 million in provisions for repair costs and
“contractual penalties”.
Ofgem said that National Grid and Scottish Power had been officially
required to deliver the link by March 2017 but that it was made fully
available only in December, before the latest fault.
Ofgem said opening of the investigation “does not imply that we have made
any findings about noncompliance.”

SAS Volunteer

We publish content from 3rd party sources for educational purposes. We operate as a not-for-profit and do not make any revenue from the website. If you have content published on this site that you feel infringes your copyright please contact: webmaster@scotlandagainstspin.org to have the appropriate credit provided or the offending article removed.

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *